Project Summary
The Magnolia Interconnection Project is a pipeline project that strengthens our community's water future.
Western Water is creating a pipeline connection with Riverside Public Utility (RPU) that will allow more water reliability for our wholesale community. It establishes a vital link between RPU and Western Water. The project is a testament to our commitment to providing consistent, high-quality water services to our valued customers.
Timeline
Oct. to Dec. 2023
Preconstruction activity will begin
Jan. 2024
Construction will start on Sterling Ave.
June 2024
Construction wraps up
July 2024
Final street paving starts